Bathroom renovations are one of the most requested jobs in UK domestic building — and one of the trickiest to price. The range from a basic suite swap to a high-spec en-suite wet room is enormous, and customers often don't know the difference until they see the quote. Here's how to price bathrooms properly.
These are all-in prices including labour and materials at a mid-spec finish, for an average-sized bathroom (4–6 m²). Larger bathrooms or premium materials will push these higher.
| Type | Cost range | What's included |
|---|---|---|
| Basic suite swap (bath, basin, WC) | £1,800 – £3,500 | Like-for-like replacement, no layout change, no retiling |
| Full strip and refit | £4,000 – £7,000 | New suite, full retile, new flooring, new lighting |
| Mid-range renovation | £6,000 – £10,000 | Better suite, full tile, underfloor heating, new extractor |
| High-spec / designer bathroom | £10,000 – £20,000+ | Premium suite, large format tile, bespoke storage, wet room |
| En-suite (typically smaller) | £3,500 – £8,000 | New build or conversion of existing space |
| Wet room conversion | £5,000 – £12,000 | Tanking, level access drain, frameless screen |
A full bathroom renovation typically involves four trades. Here's a realistic time estimate for a standard bathroom refit:
| Trade | Days | What they do |
|---|---|---|
| Labourer (strip out) | 1 day | Remove existing suite, take out old tiles |
| Plumber (first fix) | 1 – 2 days | Move or extend pipework, install waste |
| Electrician | 1 day | Zone-compliant circuits, extractor fan, lighting |
| Tiler | 2 – 5 days | Depends on room size and tile size (large tiles take longer) |
| Plumber (second fix) | 1 – 2 days | Fit suite, connect everything up |
| Flooring / finishing | 0.5 – 1 day | Floor tile, skirting, silicone sealing |
Customers often ask why quotes vary so much. Here are the factors that make a bathroom more expensive:
When customers supply their own sanitaryware, always check the delivery date before you schedule the job. A customer who ordered a bath suite with a six-week lead time and books you in for next week is one of the most common causes of downtime for bathroom fitters.